| Step 1 |
Register your project online with the Municipality of Abu Dhabi City Construction Permit Directorate (CPD) application system |
| Step 2 |
Download the required Estidama forms |
| Step 3 |
Fill in the forms and submit Estidama 1 requirements |
| Step 4 |
Upload completed forms to the attachments tab of the CPD application system |
| Step 5 |
All compliant submissions will receive Estidama 1 conditional approval |
| Step 6 |
Proceed with architectural/structural/parking/entrances review |
| Step 7 |
All compliant submissions will receive building permit conditional approval |
| Step 8 |
Fill in the forms and submit Estidama 2 requirements |
| Step 9 |
Upload completed forms to the attachments tab of the CPD application system |
| Step 10 |
All compliant submissions will receive Estidama 2 approval |
| Step 11 |
All submissions that receive Estidama 1 & 2 approvals and pass the architectural/structural/parking/entrances review will receive a building permit |